Krapkowice, Poland
Two Kaplan turbines = 1.2 MW Installed Power

Project Highlights:

The installation of the two new turbines at Krapkowice were the 22nd installation for Mavel in Poland.  Severe flooding during the civil construction delayed the project which was successfully completed in late 2006.


Project Facts:

Odra river, Krapkowice, Poland

Elektrownie Górnej Odry, Spólka z o.o.

New

Head = 2.31 m
Flow = 31 cms

Two KP2500K3 Kaplan

1.26 MW (630 kW per unit)

Turbines
Generators
Electrical Equipment
Draft Tubes
Lubrication Set
Cooling Set
Gearboxes

December 2006

« back

2
One Turbine installed

The Krapkowice site just prior to completion